Cole County
• U.S. 63 between U.S. 50 and Missouri 28 in Maries County — Concrete repair continues. The project is scheduled for completion in November.
• Route C between U.S. 54 and Missouri 52 in Morgan County — Guardrail installation, milling and resurfacing continues. The project is scheduled for completion in November.
Boone County
• U.S. 63 over Bonne Femme Creek, south of Discovery Parkway — Bridge rehabilitation in the northbound lanes continues. The project is scheduled for completion in late August.
• Missouri 163 between routes H and K — Roadway resurfacing and shoulder widening continues. The project is scheduled for completion in November.
• Providence Road between Interstate 70 and Route K — Signal upgrades, sidewalk repair and ADA improvements in various locations continue. The project is scheduled for completion in August 2020.
• College Avenue between Stadium Boulevard and Business Loop 70 — Signal upgrades, sidewalk repair and ADA improvements in various locations continue. The project is scheduled for completion in November.
• Route Y between routes M and J in Callaway County — Roadway resurfacing and shoulder widening continues. The project is scheduled for completion in November.
Callaway County
• Route J between Route Y and County Road 328 — Culvert pipe replacement will take place Monday through Thursday, Aug. 29.
• Route O between Route D and State Street — Resurfacing, shoulder additions and ADA improvements continue. The project is scheduled for completion in November.
• Route Y between routes J and M in Boone County — Roadway resurfacing and shoulder widening continues. The project is scheduled for completion in November.
Camden County
• Missouri 5 between U.S. 54 and Pier Thirty-One Road — Roadside maintenance continues. The project is scheduled for completion in late August.
• U.S. 54 over Niangua Arm — Bridge inspection will take place Monday. The inspection will take place under the bridge and is not expected to impact roadway travel.
• Route C between Route A and Missouri 17 in Miller County — Pavement repair will take place Monday through Thursday, Aug. 29.
• Route J over the Little Niangua River north of Deer Meadow Road — Bridge construction is complete. The bridge was opened to traffic Aug. 15.
• Route KK between Osage Beach Parkway and Turkey Bend Road — Sidewalk improvements and signal installation continues until late August.
Cooper County
• I-70 between mile markers 98 and 101 — Concrete replacement will take place Sunday through Wednesday.
Maries County
• U.S. 63 between Missouri 28 and U.S. 50 in Cole County — Concrete repair continues. The project is scheduled for completion in November.
• Route N between Missouri 28 and 133 — Roadway patching will take place Monday through Thursday, Aug. 29.
Miller County
• Missouri 17 between Missouri 52 and Route K — Pavement repair will take place Monday through Thursday, Aug. 29.
• Route C between Missouri 17 and Route A in Camden County — Pavement repair will take place Monday through Thursday, Aug. 29.
• Route EE between Missouri 17 and Route U — Pavement repair will take place Monday through Thursday, Aug. 29.
Moniteau County
• Missouri 87 between Route O and Missouri 5 in Cooper County — Microsurfacing continues. The project is scheduled for completion in September.
• Route C between U.S. 54 in Cole County and Missouri 52 in Morgan County — Guardrail installation, milling and resurfacing continues. The project is scheduled for completion in November.
• Route C between Route CC and Missouri 52 in Morgan County — Roadside maintenance will take place Monday through Thursday, Aug. 29.
Morgan County
• Missouri 135 between Route M and Pyrmont Road — Culvert pipe replacement will take place Monday.
• Route C between Missouri 52 and U.S. 54 in Cole County — Guardrail installation, milling and resurfacing continues. The project is scheduled for completion in November.
• Route C between Missouri 52 and Route CC in Moniteau County — Roadside maintenance will take place Monday through Thursday.
Osage County
• U.S. 63 at Missouri 133 — Intersection improvements continue. The project is scheduled for completion in November.
• U.S. 63 between U.S. 50 in Cole County and Missouri 28 in Maries County — Concrete repair continues. The project is scheduled for completion in November.
• Route C between Missouri 100 and Route A — Chip seal and guardrail installation is underway. The project is scheduled for completion in October.
• Route D between Missouri 89 and Route A — Pavement repair will take place Monday and Friday, Aug. 30.
• Route P between U.S. 63 and Missouri 133 — Culvert pipe replacement will take place Monday through Friday, Aug. 30.
• Route T between U.S. 63 and Route AA — Culvert pipe replacement will take place Monday through Friday, Aug. 30.
• Route W between U.S. 50 to Route A — Chip seal and guardrail installation continues. The project is scheduled for completion in October.