The following is the Missouri Department of Transportation's listing of general highway maintenance and construction work in the Mid-Missouri area for Aug. 12-23.
Cole County
U.S. 54 over the Missouri River - Roadway lighting maintenance in the westbound lanes will take place Wednesday.
U.S. 54 at Jefferson Street - Roadway lighting maintenance in the westbound lanes will take place Wednesday.
U.S. 63 between U.S. 50 and Missouri 28 in Maries County - Concrete repair continues. The project is scheduled for completion in November.
Route C between U.S. 54 and Missouri 52 in Morgan County - Guardrail installation, milling and resurfacing continue. The project is scheduled for completion in November.
Route HH between Route C and the Moniteau County line - Pavement repair will take place Monday through Aug. 22.
Boone County
U.S. 63 over Bonne Femme Creek, south of Discovery Parkway - Bridge rehabilitation in the northbound lanes continues. The project is scheduled for completion in late August.
Missouri 163 between routes H and K - Roadway resurfacing and shoulder widening continue. The project is scheduled for completion in November.
Providence Road between I-70 and Route K - Signal upgrades, sidewalk repair and ADA improvements in various locations continue. The project is scheduled for completion in August 2020.
College Avenue between Stadium Boulevard and Business Loop 70 - Signal upgrades, sidewalk repair and ADA improvements in various locations continue. The project is scheduled for completion in November.
Route Y between routes M and J in Callaway County - Roadway resurfacing and shoulder widening continue. The project is scheduled for completion in November.
Route HH between routes B and Z - Pavement repair will take place Monday and Tuesday.
Callaway County
Route J between Route F and County Road 252 - Culvert pipe replacement will take place Monday through Thursday.
Route J between Route Y and County Road 328 - Culvert pipe replacement will take place Monday through Thursday.
Route O between Route D and State Street - Resurfacing, shoulder additions and ADA improvements continue. The project is scheduled for completion in November.
Route Y between routes J and M in Boone County - Roadway resurfacing and shoulder widening continue. The project is scheduled for completion in November.
Camden County
Missouri 5 between U.S. 54 and Pier Thirty-One Road - Roadside maintenance continues. The project is scheduled for completion in late August.
Route J over the Little Niangua River north of Deer Meadow Road - New bridge construction continues. The roadway is closed until late August.
Route KK between Osage Beach Parkway and Turkey Bend Road - Sidewalk improvements and signal installation continues until late August.
Maries County
U.S. 63 between Missouri 28 and U.S. 50 in Cole County - Concrete repair continues. The project is scheduled for completion in November.
Route N between Missouri 28 and 133 - Roadway patching will take place Monday through Aug. 22.
Miller County
Route Z between routes W and Y - Pavement repair will take place Monday through Thursday.
Route CC between Missouri 52 and Route OO - Pull paving will take place Monday through Thursday.
Moniteau County
Missouri 87 between Route O and Missouri 5 in Cooper County - Microsurfacing continues. The project is scheduled for completion in September.
Route C between U.S. 54 in Cole County and Missouri 52 in Morgan County - Guardrail installation, milling and resurfacing continue. The project is scheduled for completion in November.
Route C between Route CC and Missouri 52 in Morgan County - Roadside maintenance will take place Monday through Thursday.
Route N between Missouri 87 and Route NN in Cole County - Roadway patching will take place Monday through Aug. 22.
Route O at Painters Road - Culvert pipe replacement will take place Monday through Aug. 22.
Business 50 between Roache and Thomas streets - Culvert pipe replacement will take place Monday through Aug. 22.
Morgan County
Route C between Missouri 52 and U.S. 54 in Cole County - Guardrail installation, milling and resurfacing continue. The project is scheduled for completion in November.
Route C between Missouri 52 and Route CC in Moniteau County - Roadside maintenance will take place Monday through Thursday.
Osage County
U.S. 63 at Missouri 133 - Intersection improvements continue. The project is scheduled for completion in November.
U.S. 63 between U.S. 50 in Cole County and Missouri 28 in Maries County - Concrete repair continues. The project is scheduled for completion in November.
Route C between Missouri 100 and Route A - Chip seal and guardrail installation is underway. The project is scheduled for completion in October.
Route P between U.S. 63 and Missouri 133 - Culvert pipe replacement will take place Monday through Aug. 23.
Route T between U.S. 63 and Route AA - Culvert pipe replacement will take place Monday through Aug. 23.
Route W between U.S. 50 to Route A - Chip seal and guardrail installation continue. The project is scheduled for completion in October.