Nov. 5-11 Mid-Missouri roadwork

Cole County

• U.S. 50 Outer Road between Business Route 50 and Country Club Drive — Pavement repairs to the roadway and adjoining entrance and exit ramps are underway. One lane will be open, and crews will flag traffic through the work area.

• Missouri 17 between U.S. 54 and Route H in Miller County — Drainage repair will take place Monday through Friday. One lane will be open, and crews will flag traffic through the work area.

Callaway County

• Business 54 between U.S. 54 East and U.S. 54 West — Sidewalk and ADA improvements continue. Asphalt paving operation will take place during the overnight hours this coming week. Pavement repair and sidewalk work continues during the daytime hours. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in December.

• Route BB between U.S. 54 and Route AA — Pavement milling will take place Monday through Friday. One lane will be open, and crews will flag traffic through the work area.

• Route YY between Interstate 70 and County Road 197 — Culvert-pipe replacement will take place Monday. The road will be closed from 9 a.m.-2 p.m. Motorists are advised to seek an alternate route around the work area.

Camden County

• U.S. 54 between Missouri 5 and Key Largo Road — Pavement improvement and j-turn installation will begin Monday, Nov. 12. One eastbound lane and one westbound lane will be open through the work area. The project is scheduled for completion in August 2019.

Cooper County

• I-70 over the Missouri River, west of the Boone County line — Bridge maintenance in the eastbound lanes will take place Sunday and Monday. One eastbound lane will be open through the work area.

• Missouri 5 over the Missouri River — Bridge maintenance will take place Tuesday through Friday. One lane will be open, and crews will flag traffic through the work area.

Maries County

• U.S. 63 over the Gasconade River, south of County Road 325 — Bridge maintenance will take place Monday through Friday. One lane will be open, and crews will flag traffic through the work area.

• Missouri 68 between Route P and County Road 431 — Roadside maintenance will take place Monday through Friday. One lane will be open, and crews will flag traffic through the work area.

Miller County

• U.S. 54, east of Missouri 87 — Bridge deck rehabilitation in the eastbound lanes is underway. One eastbound lane will be open through the work area. The project is scheduled for completion in late December.

• U.S. 54 over Wrights Creek, east of Copperhead Road — Bridge deck rehabilitation in the eastbound and westbound lanes continues. One eastbound lane and one westbound lane will be open through the work area. The project is scheduled for completion in mid-November.

• Missouri 17 between Route H and U.S. 54 in Cole County — Drainage repair will take place Monday through Friday. One lane will be open, and crews will flag traffic through the work area.

• U.S. 54 between Missouri 242 and Jeffries Road — Roadside maintenance will take place Tuesday, Nov. 13, through Friday, Nov. 16. One lane will be open, and crews will flag traffic through the work area.

• Route H between Missouri 17 and Jim Henry Road — Culvert-pipe replacement and repair in various locations will take place Monday through Friday. One lane will be open, and crews will flag traffic through the work area.

• Business 54 between U.S. 54 and Route CC — Edge rut repair will take place Tuesday, Nov. 13, through Friday, Nov. 16. One lane will be open, and crews will flag traffic through the work area.

Moniteau County

• Missouri 5 between U.S. 50 and Missouri 52 in Morgan County — Microsurfacing continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in mid-November.

• U.S. 50 between Ferguson Avenue and Sunrise Road – Shoulder repair will take place Monday and Tuesday. One lane will be open, and crews will flag traffic through the work area.

Morgan County

• Missouri 5 between Missouri 52 and U.S. 50 in Moniteau County – Microsurfacing continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in mid-November.

• Missouri 52 between Missouri 5 and the Benton County line – Microsurfacing continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in mid-November.

Osage County

• Missouri 100 between Missouri 89 and Chamois Power Plant Road – Shoulder repair will begin Monday. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in mid-December.

• Route DD between Route U and County Road 610 — Pavement repair will take place Monday through Friday, Nov. 16. One lane will be open, and crews will flag traffic through the work area.