U.S. 54 between Broadway Street and Stadium Boulevard - Roadway resurfacing, pavement repair, guard rail replacement and bridge repair continue. The project is in its third stage, which includes rehabilitation of the westbound U.S. 54 bridges over Stadium Boulevard and Broadway Street and work on the U.S. 54 on-ramp from the Madison Street bridge. Westbound U.S. 54 is reduced to one lane 24 hours a day from north of Broadway Street to south of Stadium Boulevard. The U.S. 54 on-ramp from Madison Street is closed. The work on westbound U.S. 54 and Madison Street exit is scheduled for completion in early August. The entire project is scheduled for completion in November.

Missouri 17 between U.S. 54 and Missouri 52 Miller County - Roadway resurfacing and shoulder widening continue. Concrete replacement will take place just north of the Saline Creek bridge this week. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Boone County

Route B between Business Loop 70 and Brown Station Road - Roadway resurfacing and sidewalk improvements are nearing completion. Asphalt work will take place south of Hallsville this week. Occasional lane closures are possible.

U.S. 40 between Route UU and Missouri 5 in Howard County - Resurfacing and shoulder improvements continue. Resurfacing operations on the west end of the project will take place this week. Concrete work is planned at Booth Lane and Trails West. One lane will be open, and a pilot car will guide traffic. The project is scheduled to be completed in October.

U.S. 63 between Missouri 22 and Route EE in Randolph County - Roadway resurfacing in the northbound lanes is underway. One northbound lane will be open. The project is scheduled for completion in November.

Route J between U.S. 40 and Missouri 124 - Roadway paving will take place Monday through Thursday. One lane will be open, and crews will flag traffic.

Callaway County

U.S. 54 bridge improvements - Guard cable installation on eastbound and westbound U.S. 54 from Holts Summit to Route HH in Fulton continues. Bridge rehabilitation work on the eastbound U.S. 54 bridge over Stinson Creek continues. One eastbound lane of U.S. 54 will be closed. These traffic impacts are scheduled until the end of July.

Route A between I-70 and Route B - Pavement patching will take place July 30 through Aug. 2. One lane will be open, and crews will flag traffic.

Route B between U.S. 54 and the Montgomery County line - Roadway resurfacing continues. Guardrail installation at the Harrison Branch bridge will take place this week. One lane will be open, and crews will flag traffic. The project is scheduled for completion in October.

Route E between Route DD and Old U.S. 54 - Roadway resurfacing and sidewalk upgrades continue. Resurfacing west of Auxvasse will take place this week. In addition, sidewalk work continues in the city of Auxvasse. One lane will be open, and crews will flag traffic. The project is scheduled for completion in October.

Route A between I-70 and Route B - Pavement patching will take place Monday through Thursday. One lane will be open, and crews will flag traffic.

Business 54 between U.S. 54 East and U.S. 54 West - Sidewalk and ADA improvements are underway. One lane will be open, and crews will flag traffic. The project is scheduled for completion in December.

Camden County

Missouri 5 between Missouri 7 and Beauty Road Roadway resurfacing continues. Striping operations will take place this week. One lane will be open, and crews will flag traffic.

Missouri 5 between Missouri 7 and Missouri 64 in Laclede County - Guardrail installation and replacement and pavement repair continue. Paving operations will take place from 7 p.m.-7 a.m. each weekday. One lane will be open, and crews will flag traffic. The entire project is scheduled for completion in November.

Route O between U.S. 54 and Rooffner Road - Pavement repair will take place Monday through Aug. 2. One lane will be open, and crews will flag traffic.

Cooper County

Missouri 87 over I-70 - Bridge replacement is underway. Grading operations will take place this week. The removal of the Missouri 87 overpass bridge over I-70 will begin July 27. I-70 will be closed in both directions at 10 p.m. July 27 and re-opened by 5 a.m. July 30. During the closure, I-70 traffic will be detoured onto the exit and entrance ramps at the interchange, while there will be no access to I-70 from Missouri 87. The entire project is scheduled for completion in November.

Route U over Petite Saline Creek, south of Debo Road - Bridge maintenance will take place Monday and Tuesday. One lane will be open, and crews will flag traffic.

Route BB between Route A and Morgan Street - Sidewalk improvements continue.

Maries County

Missouri 28 between U.S. 63 and I-44 in Pulaski County - Chip-sealing the roadway surface to extend pavement life continues this week. Motorists should expect to encounter loose gravel on the road surface for several days after the seal coat is complete. At that time, crews will sweep the roadway. One lane will be open, and crews will flag traffic through the work area.

Missouri 42 between U.S. 63 and Missouri 17 in Miller County - Roadway resurfacing, shoulder addition and guardrail installation continue. Crews will pave asphalt this week. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Missouri 42 over the Gasconade River, east of County Road 335 - Bridge scour repair continues. The project is scheduled for completion in August.

Route BB between Missouri 133 and Missouri 42 in Miller County - Pavement patching will take place Monday through Aug. 2. One lane will be open, and crews will flag traffic.

Miller County

Route A over Tavern Creek, east of Route PP - Bridge replacement continues. The road is closed. The project is scheduled for completion in mid-August.

Missouri 17 between Missouri 52 and U.S. 54 in Cole County - Roadway resurfacing and shoulder widening continue. Concrete replacement will take place just north of the Saline Creek bridge this week. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Missouri 42 between Missouri 17 and U.S. 63 in Maries County - Roadway resurfacing, shoulder addition and guardrail installation continue. Crews will pave asphalt this week. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Route A between Missouri 17 and Missouri 42 Pavement patching will take place Monday through Aug. 2. One lane will be open, and crews will flag traffic.

Route H between Missouri 17 and Marys Home Road - Roadway resurfacing continues. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Route BB between Missouri 42 and Missouri 133 in Maries County - Pavement patching will take place Monday through Aug. 2. One lane will be open, and crews will flag traffic.

Business 54 at Eastview Drive - Drainage repair will take place Monday through Wednesday. One lane will be open, and crews will flag traffic.

Morgan County

Route J between Missouri 5 and Missouri 135 Pavement patching will take place Monday through Aug. 2. One lane will be open, and crews will flag traffic.

Route BB over Middle Richland Creek, south of Self Chapel Road - Bridge replacement continues. The road is closed. The project is scheduled for completion in August.

Route PP over Messer Creek, east of Route D - Bridge replacement continues. The road is closed. The project is scheduled for completion in August.