Mid-Missouri road work for Aug. 20-24

Cole County

U.S. 54 between Broadway Street and Stadium Boulevard - Roadway resurfacing, pavement repair, guardrail replacement and bridge repair continue. Cold milling and resurfacing operations will take place in the eastbound and westbound lanes between Stadium Boulevard and the Missouri River Bridge during overnight hours. One eastbound lane and one westbound lane will be closed with occasional closures of entrance and exit ramps. The entire project is scheduled for completion in November.

Missouri 17 between U.S. 54 and Missouri 52 Miller County - Roadway resurfacing and shoulder widening continue. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Boone County

Route BB over I-70 - Bridge rehabilitation and ramp repairs continue. The bridge will close Monday. Entrance and exit ramps will remain open through much of the project but may close for resurfacing near the end of the project. The project is scheduled for completion in October.

Callaway County

U.S. 54 between Route F and Route HH - Concrete patching in the eastbound lanes will take place Monday and Tuesday. One eastbound lane will be open.

Route A between I-70 and Route B - Pavement patching will take place Monday through Aug. 30. One lane will be open, and crews will flag traffic.

Route B between U.S. 54 and the Montgomery County line - Roadway resurfacing continues. Guardrail installation at the Harrison Branch and Loutre River bridges will take place this week. One lane will be open, and crews and a pilot car will guide traffic. The project is scheduled for completion in October.

Business 54 between U.S. 54 East and U.S. 54 West - Sidewalk and ADA improvements continue. One lane will be open, and crews will flag traffic. The project is scheduled for completion in December.

Cooper County

Missouri 87 over I-70 - Bridge replacement is underway and Missouri 87 is closed, but eastbound exit and entrance ramps connecting to I-70 remain open. Signed detours are in place. Occasional overnight lane closures are possible on I-70 for construction of the new bridge. Grading operations, base rock installation, resurfacing of Missouri 87 and the westbound entrance and exit ramps and culvert extension work will take place this week. The entire project is scheduled for completion in November.

Maries County

Missouri 42 between U.S. 63 and Missouri 17 in Miller County - Roadway resurfacing, shoulder addition and guardrail installation continue. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Route T between Missouri 42 and Route AA - Culvert pipe replacement will take place Monday through Thursday. One lane will be open, and crews will flag traffic.

Miller County

Missouri 17 between Missouri 52 and U.S. 54 in Cole County - Roadway resurfacing and shoulder widening continue. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Missouri 42 between Missouri 17 and U.S. 63 in Maries County - Roadway resurfacing, shoulder addition and guardrail installation continue. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Route A between Missouri 17 and Missouri 42 - Pavement patching will take place Monday through Aug. 30. One lane will be open, and crews will flag traffic.

Route H between Missouri 17 and Marys Home Road - Roadway resurfacing continues. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Route M between Missouri 87 and Saline Road - Pavement milling will take place Thursday through Aug. 30. One lane will be open, and crews will flag traffic.

Moniteau County

U.S. 50 between Missouri 5 and Independence Avenue - Box culvert maintenance will take place Tuesday and Wednesday. One lane will be open, and crews will flag traffic.

Route E between U.S. 50 and Route CC - Partial pavement overlay will take place Wednesday then again Aug. 27-28. One lane will be open, and crews will flag traffic.

Route F between Missouri 87 and Route E - Partial pavement overlay will take place Monday through Wednesday. One lane will be open, and crews will flag traffic.

Morgan County

Route BB over Middle Richland Creek, south of Self Chapel Road - Bridge replacement is nearing completion. The road is closed.

Osage County

Route A between U.S. 50 and Main Street - Roadway resurfacing continues. One lane will be open, and crews will flag traffic. The project is scheduled for completion in October.

Route K between Missouri 89 and County Road 318 - Roadway patching will take place Monday through Aug. 30. One lane will be open, and crews will flag traffic.

Route W between U.S. 50 and Route A - Roadway patching will take place Monday through Aug. 30. One lane will be open, and crews will flag traffic.