Mid-Missouri road work for Aug. 6-10

Cole County

• U.S. 54 between Broadway Street and Stadium Boulevard — Roadway resurfacing, pavement repair, guard rail replacement and bridge repair continue. Cold milling and resurfacing operations will take place in the eastbound lanes between Missouri Boulevard and the Missouri River Bridge during overnight hours. One eastbound lane will be closed with occasional closures of entrance and exit ramps. The entire project is scheduled for completion in November.

• Missouri 17 between U.S. 54 and Missouri 52 in Miller County — Roadway resurfacing and shoulder widening continue. Concrete replacement will take place just north of the Saline Creek bridge this week. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

• Route B between Missouri 179 and Missouri 133 in Osage County — Ditch work will take place Monday through Aug. 16. One lane will be open, and crews will flag traffic.

Boone County

• I-70 between U.S. 63 and Stadium Boulevard — Pavement leveling in the eastbound and westbound lanes will take place Sunday through Thursday. One eastbound lane and one westbound lane will be open.

• Route BB over I-70 — Bridge rehabilitation and ramp repair is scheduled to begin Thursday. The eastbound entrance and exit ramps will be closed from 10 p.m. Thursday until 5 a.m. Friday. The ramps will temporarily reopen then close again for pavement repair from 7 p.m. Friday until 5 a.m. Aug. 13. One eastbound and one westbound lane of I-70 will close during nighttime hours during the week of Aug. 13 for repairs to the Route BB overpass. The westbound entrance and exit ramps will be closed from 10 p.m. Aug. 16 until 5 a.m. Aug. 17. The ramps will temporarily reopen then close again for pavement repair from 7 p.m. Aug. 17 until 5 a.m. Aug. 20. The full project is scheduled for completion in October.

Callaway County

• U.S. 54 between I-70 and Route J — Guardrail installation in the eastbound and westbound lanes continues this week. One eastbound lane and one westbound lane will be open.

• Route A between I-70 and Route B — Pavement patching will take place Monday through Aug. 16. One lane will be open, and crews will flag traffic.

• Route B between U.S. 54 and the Montgomery County line — Roadway resurfacing continues. One lane will be open, and crews and a pilot car will guide traffic. The project is scheduled for completion in October.

• Business 54 between U.S. 54 East and U.S. 54 West — Sidewalk and ADA improvements continue. One lane will be open, and crews will flag traffic. The project is scheduled for completion in December.

Cooper County

• Missouri 87 over I-70 — Bridge replacement continues and Missouri 87 is closed, but exit and entrance ramps connecting to I-70 remain open. Missouri 87 north of I-70 is scheduled to close for two weeks beginning Aug. 13, as the roadbed will be raised. Occasional overnight lane closures are possible on I-70 for construction of the new bridge. Grading operations will take place this week. The entire project is scheduled for completion in November.

Maries County

• Missouri 42 between U.S. 63 and Missouri 17 in Miller County — Roadway resurfacing, shoulder addition and guardrail installation continue. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Miller County

• Route A over Tavern Creek, east of Route PP — Bridge replacement continues. The road is closed. The project is scheduled for completion in mid-August.

• Route A between Missouri 17 and Missouri 42 — Pavement patching will take place Monday through Aug. 16. One lane will be open, and crews will flag traffic.

• Route H between Missouri 17 and Marys Home Road — Roadway resurfacing continues. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

Morgan County

• Route BB over Middle Richland Creek, south of Self Chapel Road — Bridge replacement continues. The road is closed. The project is scheduled for completion in mid-August.

• Route HH between Missouri 5 and Route E — Pavement patching will take place Monday through Aug. 16. One lane will be open, and crews will flag traffic.

• Route PP over Messer Creek, east of Route D — Bridge replacement continues. The road is closed. The project is scheduled for completion in mid-August.